Objective:

Achieve fully automated operation of the AR-1500 turbine and provide power to the grid at the correct voltage and frequency.

Deliverables:

D9.1: Initial AR Series turbine producing power to the Scottish National Grid

Progress:

This WP is now complete following the grid connection and commissioning of the Ar1500 turbine in 2017.