MeyGen

In 2010, as part of the Pentland Firth and Orkney Waters leasing round, The Crown Estate awarded an agreement for lease to MeyGen Limited, granting the option to develop a tidal stream project of up to 398MW at an offshore site between Scotland’s northernmost coast and the island of Stroma, as shown in the map below.

The 3.5km site covers some of the fastest flowing waters in the UK, just 2km from Scotland’s north-east tip. To the north of the site is the uninhabited island of Stroma, which creates a natural channel with the mainland to accelerate the millions of tonnes of water flowing between the North Sea and the Atlantic Ocean every day. This site was originally identified by Atlantis in 2007, following a global review of tidal resource which concluded that the high flows, medium water depths and proximity to the mainland rendered it a prime location for development.

The MeyGen project is currently the largest planned tidal stream project in the world and is the only commercial multi-turbine array to have commenced construction. The project is split into phases as follows:

MeyGen Phase 1A

Status: Operational

The first phase of the MeyGen project (Phase 1A) involves the deployment of 4 No. 1.5MW turbines installed on gravity turbine support structures as part of MeyGen’s “deploy and monitor strategy” and will act as a precursor to the development of the remaining consented 86MW project. The project will demonstrate that the development of tidal array projects is both commercially viable and technically feasible, with the invaluable lessons drawn from the construction, installation, operation and maintenance of this phase (of the project) fed into subsequent phases.

Each turbine is located on an individual foundation weighing between 250 and 350 tonnes, coupled with 6 ballast blocks weighing 1,200 tonnes, that provide horizontal stability over the lifetime of the turbine. Each turbine has a dedicated subsea array cable laid directly on the seabed and brought ashore via a horizontal directionally drilled borehole within the foreshore bedrock.

The turbines feed into the onshore power conversion unit building at the Ness of Quoys, where the low voltage supply will be converted to 33kV for export via the 14.9MW grid connection into the local distribution network. On completion, this phase of the tidal array will generate sufficient electricity to supply 2,600 homes.

The planning consent for Phase 1 includes three power conversion unit buildings, which have been designed in consultation with The Highland Council and Scottish Natural Heritage as modern functional industrial buildings that reflect their landscape and historic environmental context.

Phase 1A will incorporate two different turbine technologies (Atlantis Resources AR1500 and Andritz Hydro Hammerfest AH1000 MK1), with environmental monitoring equipment installed that will assess the interaction between the tidal turbines and the marine environment, including marine mammals. The results of the monitoring work will be used to inform subsequent phases of the project.

The key milestones achieved to date are:

  • Crown Estate Agreement Lease – October 2010
  • Marine Licence granted by Marine Scotland – January 2014
  • Financial Close/Construction contracts conclude – September 2014
  • Construction commences at the Ness of Quoys site – January 2015
  • Offshore subsea array cables installed in Inner Sound – October 2015
  • Onshore building works complete, and grid connection energised – June 2016
  • Offshore installation of foundations and turbines commenced – October 2016
  • First electrons exported to grid – November 2016
  • ROC and Ofgem accreditation –– March 2017
  • 1GWh exported to the grid – August 2017
  • MeyGen Phase 1A formally enters 25-year operations phase– April 2018
  • 17GWh exported to grid – June 2019

_m0r0327

The supply chain for the Phase 1A project is spread across the United Kingdom, Europe and North America; 43% of the project’s expenditure is in Scotland and involves companies based in Caithness, and Ross and Cromarty.

2016-10-10-06-02-40

MeyGen has developed an active network management scheme with Lochend Windfarm (currently under construction), which will permit this windfarm to export to the local distribution network utilising the existing Phase 1A grid connection.

PROJECT STROMA (formally known as MeyGen Phase 1B)

Status: in Construction

Project Stroma is a subsea hub at Atlantis’ MeyGen site which will allow multiple turbines to be connected to a single power export cable. This will significantly reduce the costs associated with grid connection. The length of power export cable as well as the amount of onshore conversion equipment required for grid connection will be significantly reduced, as will the amount of horizontal directional drilling and the amount of vessel time required for cable installation.

Project Stroma will connect two additional Atlantis AR2000 turbines via the new subsea hub to a single power export cable which will then be connected via the MeyGen substation to the National Grid.

MeyGen Phase 1C

Status: in Development

Atlantis has full consent, all necessary permission and grid capacity for Phase 1C. We will build an additional 49 (73.5 MW) turbines at MeyGen at an estimated cost of £420m. The project will be transformational for the tidal energy industry, providing the necessary scale to justify the establishment of turbine manufacturing facilities at Global Energy’s facility in Nigg Energy Park.

The project will also provide an investment opportunity for commercial debt and equity providers to invest in tidal stream projects. In addition, Phase 1C will create an estimated 5,300 full time roles, repurposing jobs from the oil and gas sector and placing Scotland at the forefront of an estimated 25GW global export market for decades to come, as well as significantly reducing LCOE.

Phase 2 and 3

Status: in Development

The MeyGen offshore lease currently permits up to 398MW of tidal stream capacity to be installed within the site. While presently MeyGen only has grid capacity for up to 252MW, the site is capable of supporting the full project buildout.

This implies a potential Phase 3 project of 146MW which, subject to grid connection, turbine availability and speed of installation is scheduled for deployment following completion of Phase 2. Subsequent phases of the MeyGen project will provide commercial investment opportunities for major equity and debt providers, infrastructure and pension funds who currently invest in other forms of renewable energy such as offshore wind.

Project Clearwater